Question: Looking at the project network below, which activity would you crash first? Assume they all cost the same to crash. The numbers are duration in

 Looking at the project network below, which activity would you crash

Looking at the project network below, which activity would you crash first? Assume they all cost the same to crash. The numbers are duration in days. G-F F-E C-D S-A first? Assume they all cost the same to crash. The numbers are