Question: looking to get help. please address this problem...other experts seem to copy and paste answers to similar question, not this one. 2. Activity Immediate Optimistic
looking to get help. please address this problem...other experts seem to copy and paste answers to similar question, not this one.
2. Activity Immediate Optimistic Most Likely Pessimistic Expected Variance Predecessor Time (Days) Time (Days) Time (Days) Time A 4 6 8 B 2 5 14 A 4 8 12 D 5 7 9 (a) Calculate Expected Time and Variance for the activities indicated and complete the table above. (b) Draw the Precedence Diagram for the above project complete with ES, EF, LS, and LF. (c) Compute the Critical Path and calculate the Project Completion Time. (d) What is the probability that the project can be completed within 15 days
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock