Question: Lot Size Lead Time: 2 weeks 7 8 1 2 3 4 5 6 10 Item XYZ Description Date Gross requirements Scheduled receipts 25 75
Lot Size Lead Time: 2 weeks 7 8 1 2 3 4 5 6 10 Item XYZ Description Date Gross requirements Scheduled receipts 25 75 100 75 50 Projected on Hand 40 Planned receipts Planned order releases Use the information in the table above. If an FOQ of 100 units is used, how many planned order releases are there for item XYZ? a. Zero or one b. Two or three OcFour or five d. More than five