Question: Low - level coding logic in Material Requirements Planning calculations ensures that... Select one: a . Only purchased parts are calculated in the MRP process.

Low-level coding logic in Material Requirements Planning calculations ensures that...
Select one:
a.
Only purchased parts are calculated in the MRP process.
b.
Parts are planned in the defined lot size.
c.
All of the component's gross requirements are taken into account prior to calculating net requirements and planned order releases.
d.
The MRP computer program runs as quickly as possible.