Question: Lunches are prepared in a two step process with two sequential resources. The processing time at the first resource is 3 9 minutes and for

Lunches are prepared in a two step process with two sequential resources. The processing time at the first resource is 39 minutes and for the second resource it is 36 minutes. The first resource has 9 workers and the second resource has 8 workers.
What is the capacity of this process in terms of lunches per hour?