Question: M 6 _ 4 . A software installation project is being reviewed. Assume the project must be completed in 1 6 weeks. Crash the project
M A software installation project is being reviewed. Assume the project must be completed in
weeks. Crash the project as necessary crashing one week at a time The relevant information is in the
table below.
Crash the project from to weeks by week increments and answer the following questions:
a Which activities are on the critical path before you start crashing the project
b What is the crash cost per week for Activity A
c By how many weeks can Activity D be crashed?
d To crash the project from weeks to weeks, which activity would you crash by one week?
e To crash the project from weeks to weeks, which activity would you crash by one week?
f To crash the project from weeks to weeks, which activity would you crash by one week?
g To crash the project from weeks to weeks, which activity would you crash by one week?
h To crash the project from weeks to weeks, which activitys would you crash by one week?
i What is the total crashing cost to crash the project from weeks to weeks?
j After crashing your project to weeks how many critical paths does your project have?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock