Question: M17 A new order lling system needs to be installed as soon as possible. The table below lists the project's activities and their predecessors. Also

M17 A new order lling system needs to be installed as soon as possible. The table below lists the project's activities and their predecessors. Also provided is the cost information to reduce the standard activity times. acnwnr IMMEDIATE SETTLE?\" STANDARD CT'll'MlsEH CRASH Pneoecessons COST COST tom's) toms) B A 10 $3,000 8 54,700 D C 6 $1,600 4 $2,600 r o, E 5 $1,200 3 $2,300 H F, G 4 52,600 3 53,800