M2 Five tasks to be completed on three machines
M2 Five tasks to be completed on three machines A, B and C and the sequence of work is A and then CIB The time taken is in hours for each task It is required to find the optimal sequence with the least total time taken to complete All tasks as well as finding lost time for both machines JOB 1 2 3 4 5 A 4 9 8 6 5 B 5 6 2 3 4 C 8 10 6 7 11