Question: m2 Help Save & E Submit 24 Zhang industries budgets production of 250 units in June and 260 units in July, Each finished unit requires
m2 Help Save & E Submit 24 Zhang industries budgets production of 250 units in June and 260 units in July, Each finished unit requires 5 pounds (lbs.) of raw material, which costs $6 per pound. Each month's ending inventory of raw materials should be 20% of the following month's budgeted production. The June raw materials Inventory has 250 pounds of raw material Compute the budgeted purchases for raw material in pounds for June Multiple Choice 2 1050 1250 lbs 1210 lbs 300 is