Question: M23-19. Direct Labor Variances Advanced Micro Devices develops high-performing computing products. Assume one of its processors, Ryzen 7 Pro, has a standard labor time of
| M23-19. Direct Labor Variances | |||||||
| Advanced Micro Devices develops high-performing computing products. Assume one of its processors, Ryzen 7 Pro, has a standard labor time of 0.25 hours and a standard labor rate of $20 per hour. During February, the following activities pertaining to direct labor for Ryzen 7 Pro were recorded: | |||||||
| Direct labor hours used............................................................................................................... | 64,000 | ||||||
| Direct labor cost........................................................................................................................... | $1,248,000 | ||||||
| Units of Ryzen 7 Pro manufactured........................................................................................... | 250,000 | ||||||
| Required | |||||||
| a. Determine the labor rate variance. b. Determine the labor efficiency variance. c. Determine the total flexible budget labor cost variance. | |||||||
| Standard labor time (hours) | 0.25 | ||||||
| Standard labor rate (per hours) | $20 | ||||||
| Standard hours | 62,500 | ||||||
| Labor rate variance | $32,000 | ||||||
| Labor efficiency variance | ($30,000) | ||||||
| Total flexible budget labor cost variance |
Need help figuring out the Total flexible labor cost variance.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock