Question: Machine 1 M. 2 M. 3 M. 4 M. 5 Function Mixing Adding H 2 O Adding CO 2 Bottling Adding Label Time (seconds) 10
| Machine 1 | M. 2 | M. 3 | M. 4 | M. 5 | ||
| Function | Mixing | Adding H2O | Adding CO2 | Bottling | Adding Label | |
| Time (seconds) | 10 | 9 | 26 | 17 | 1 | |
| Capacity (per second) | ||||||
| Capacity (per minute) | ||||||
| Bottle Process Capacity (per minute) | ||||||
| Demand (per minute) | 10 | 10 | 10 | 10 | 10 | |
| Flow Rate | ||||||
| Cycle Time | ||||||
| Idle Time | ||||||
| Total Idle Time | ||||||
| Labor Content | ||||||
| Hourly Wage | $ 15.00 | $ 10.00 | $ 22.00 | $ 13.00 | $ 9.00 | |
| Labor Cost per unit | ||||||
| Resource (station) utilization | ||||||
| Process utilization |