Question: Machine 3 Machine 2 Machine 4 Machine 5 Machine 1 3,1 2,6 2 15 Operation time (min): 4,3 4,0 4,9 Setup time (hours: 2 4

Machine 3 Machine 2 Machine 4 Machine 5 Machine 1
Machine 3 Machine 2 Machine 4 Machine 5 Machine 1 3,1 2,6 2 15 Operation time (min): 4,3 4,0 4,9 Setup time (hours: 2 4 5 7 Nonoperation time (hours): 13 10 15 10 in the above batch production plant setting, a batch of size 360 is routed through five machines. (a) Determine the hourly production rate (pc/hr) for each operation; (3 points each) Machine 1 Machine 2 Machine 3 Machine 4 Machine 5 (b) Determine the average manufacturing lead time (hr) (5 points)