Question: Machine A , in a manufacturing process including seven other process steps, receives an overhaul improving output of the machine by 2 5 % -

Machine A, in a manufacturing process including seven other process steps, receives an overhaul improving output of the machine by 25%-- well beyond customer demand. Despite this improvement to Machine A, the process still can't meet customer demand. Machine A is likely a __________.
Multiple choice question.
Capacity-constrained resource
bottleneck
nonbottleneck