Question: Machine Type Milling machine Lathe Grinder X , 8 A manufacturing firm has discontinued production of a certain unprofitable product line. Considerable excess production capacity

Machine Type
Milling machine
Lathe
Grinder
X,
8
A manufacturing firm has discontinued production of a certain unprofitable product line.
Considerable excess production capacity was created as a result. Management is consid-
ering devoting this excess capacity to one or more of three products: X1, X2, and X3.
Machine hours required per unit are:
Product
x2
2
3
4
2
O
X
3
0
1
Milling machines
Lathes
Grinders
The available time in machine hours per week is:
Machine Hours per Week
800
480
320
The salespeople estimate they can sell all the units of X, and X2 that can be made. But
the sales potential of X2 is 80 units per week maximum.
Unit profits for the three products are:
Unit Profits
$20
6
8
X
X.
X
a. Set up the equations that can be solved to maximize the profit per week.
b. Solve these equations using the Excel Solver.
c. What is the optimal solution? How many of each product should be made, and what
should the resultant profit be?
d. What is this situation with respect to the machine groups? Would they work at capacity,
or would there be unused available time? Will X3 be at maximum sales capacity?
e. Suppose an additional 200 hours per week can be obtained from the milling machines
by using staff overtime. The incremental cost would be $1.50 per hour. Would

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!