Question: MAJOR SUBPROJECTS/ACTIVITIES ACTIVITY IDENTIFICATION DEPENDENCY DURATION (WEEKS) Product Specifications (P) Market research P1 1 Overall product specifications P2 P1 3 Hardware P3 P2 4 Software
| MAJOR SUBPROJECTS/ACTIVITIES | ACTIVITY IDENTIFICATION | DEPENDENCY | DURATION (WEEKS) | |
| Product Specifications (P) | ||||
| Market research | P1 | 1 | ||
| Overall product specifications | P2 | P1 | 3 | |
| Hardware | P3 | P2 | 4 | |
| Software | P4 | P3 | 4 | |
| Supplier specifications (S) | ||||
| Hardware | S1 | P4 | 4 | |
| Software | S2 | P4 | 6 | |
| Product design (D) | ||||
| Battery | D1 | S1 | 1 | |
| Display | D2 | S1 | 3 | |
| Camera | D3 | S1 | 1 | |
| Outer cover | D4 | D1, D2, D3 | 3 | |
| Product integration (I) | ||||
| Hardware | I1 | D4 | 5 | |
| User interface | I2 | D2 | 3 | |
| Software coding | I3 | I2 | 3 | |
| Prototype testing | I4 | I1, I3 | 3 | |
| Subcontracting (V) | ||||
| Suppliers selection | V1 | S1 ,S2 | 9 | |
| Contract negotiation | V2 | I4, V1 | 1 | |
Your boss would like you to study the impact of making the changes to how the project is organized. The change involves using dedicated teams that would work strictly in parallel on the activities in each subproject. For example, in subproject P (product specifications) the team would work on P1, P2, P3, and P4 all in parallel. In other words, there would be no precedence relationships within a subprojectall tasks within a subproject would be worked on at the same time and each would take the same amount of time as originally specified. With this new design, all the subprojects would be done sequentially with P done first, then S, D, I, and finally V. What would be the expected impact on how long it would take to complete the project if this change were made?
options:
| |||
| |||
| |||
|
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
