Question: Make a Gantt Chart with the help of data given below. There are four activities with five time periods. Activity 1 is planned to start

Make a Gantt Chart with the help of data given below. There are four activities with five time periods. Activity 1 is planned to start in period 1 and extends for two periods, to time period 3. Activity 2 also starts at period 1 and runs parallel to activity 1 for one time period. Activity 3 starts when activity 2 completes and runs for three time period. Activity 4 starts when Activity 1 completes and runs for one time period.