Question: Make a Project Network Diagram (Chap. 5) and identify the Critical Path (including the forward pass and backward pass, late start/early start, and late finish/early
- Make a Project Network Diagram (Chap. 5) and identify the Critical Path (including the forward pass and backward pass, late start/early start, and late finish/early finish data).
- What is the project's completion date based on the date in Exhibit 1?
- Which activities do you consider the greatest risk for the project (Chap. 7)?
- What is more critical to Brent: Cost or on-time completion?
- What activities should you consider crashing and why (Chap. 9)?
- Are there opportunities to re-sequence the activities in the project to shorten the completion time?
- What action should Brent Collver take and why?
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock
