Make an economical analysis for this project as per the followings : 1- Use any one of
Fantastic news! We've Found the answer you've been seeking!
Question:
Make an economical analysis for this project as per the followings :
1- Use any one of the analysis methods ( PW or AW ) using excel sheet
2- use 5.5% per year MARR compounded monthly .
3- Assume that the payments from the government to the company be based on every three months a payment and a last payment be after 6 months after the period of one year , ( for maintenance assurances )
4- draw the cash flow diagram
Transcribed Image Text:
Division/Description A A.1 A.2 B B.1 с C1 C.1.1 C.1.2 C.2 C.2.1 C.3 C.3.1 C.3.2 C.3.3 C.3.4 C.3.5 C.4 C.4.1 C.4.2 C.4.3 GENERAL TOTAL Mobilization and Demobilization Mobilization: Mobilization of machinery, personnel and all any other material and equipment required to perform the work. Setting up the site camp including offices and accommodations cabins together with any other essential facilities. Demobilization: Demobilization of machinery, personnel and all any other material and equipment from the Worksite. Removal of the site camp including offices and accommodations cabins together with any other essential facilities from the Worksites. The Contractor shall leave the Worksite and close surrounding clean as directed by the Site Engineer. Project Supervision, Survey and Engineering Services Project Management: Supervision of all the engineering and field works. Quality Control and Ensuring all the construction works are in the conformity with the approved plans, specifications and architectural/ structural drawings. Road Construction Works Construction the road with a width of 12 m as shown in the drawings and Typical cross-section, construction the side ditches, side slope crown, cross slope, supper. elevation according to the section R5 of (IGSRB) and including cutting in all type soil (i.e. soil, rocky, semi rocky, concrete, asphalt and other layers) Earth Cutting Works: Supply materials and equipment to use in excavation of the cutting sections. Includes removal of the cutting material. Earth Filling Works: Supply materials and equipment for the filling sections. Sub-base & base layer works: Provide all requirements (including Batch plant) to lay a layer of crushed limestone base course with 40cm thick in three layers, 9 m width and well compacted to %98 of M.D.D according to the section "R7" and table ""Batch plant ksites. The Contractor shall leave the Worksite and close surrounding clean as directed by the Site Engineer.R7/1" in the "IGSRB" and the instructions of the site engineer. Culverts: Provide materials and construct complete concrete pipe & box culverts using fair face wood shuttering all exposed edge shall be chamfered. Double Box culvert 2x2 m Double Box culvert 1.5x1.5 m. Single Box culvert (1.5x1.5)m. 01 m double (Reinforced concrete) Ø1 m single (Reinforced concrete) Construction of New Pavement Prime coat to the requirements of section R&A of the IGSRB and the instructions of the Bituminous stabilizer course with the width of 7.85 meter according to the section R9 and the table R9/3 of SORB revised edition 2003 with the thickness of 10 cm. after compaction according to the site engineer and compaction of %97 density of Marshal laboratory. Notice: the rate of mixing bituminous for the stabilizer and using bulk density 40 to 50 grade and if there was any change in the mixture rate of the bituminous will be deducted according to the IGSRB of 1992 Tack coat to the requirements of section R&B of the IGSRB and the instructions of the site engineer. C.4.4 Bituminous binder course 7.5 meter wide, according to the section R9 and the table R9 Total Costs ($) 1,537,400.00 20,000.00 10,000.00 10,000.00 10,000.00 10,000.00 858,000.00 768,000.00 90,000.00 78,000.00 78,000.00 267,150.00 112,500.00 72,000.00 21,600.00 40,800.00 20,250.00 304,250.00 5,750.00 161,000.00 5,500.00 132,000.00 Total % Complete 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% Work Completed Total Completed to Previous Application date ($) 1,537,400.00 20,000.00 10,000.00 10,000.00 10,000.00 10,000.00 858,000.00 768,000.00 90,000.00 78,000.00 78,000.00 267,150.00 112,500.00 72,000.00 21,600.00 40,800.00 20,250.00 304,250.00 5,750.00 161,000.00 5,500.00 132,000.00 1,537,400.00 20,000.00 10,000.00 10,000.00 10,000.00 10,000.00 858,000.00 768,000.00 90,000.00 78,000.00 78,000.00 267,150.00 112,500.00 72,000.00 21,600.00 40,800.00 20,250.00 304,250.00 5,750.00 161,000.00 5,500.00 132,000.00 This Period ($) Division/Description A A.1 A.2 B B.1 с C1 C.1.1 C.1.2 C.2 C.2.1 C.3 C.3.1 C.3.2 C.3.3 C.3.4 C.3.5 C.4 C.4.1 C.4.2 C.4.3 GENERAL TOTAL Mobilization and Demobilization Mobilization: Mobilization of machinery, personnel and all any other material and equipment required to perform the work. Setting up the site camp including offices and accommodations cabins together with any other essential facilities. Demobilization: Demobilization of machinery, personnel and all any other material and equipment from the Worksite. Removal of the site camp including offices and accommodations cabins together with any other essential facilities from the Worksites. The Contractor shall leave the Worksite and close surrounding clean as directed by the Site Engineer. Project Supervision, Survey and Engineering Services Project Management: Supervision of all the engineering and field works. Quality Control and Ensuring all the construction works are in the conformity with the approved plans, specifications and architectural/ structural drawings. Road Construction Works Construction the road with a width of 12 m as shown in the drawings and Typical cross-section, construction the side ditches, side slope crown, cross slope, supper. elevation according to the section R5 of (IGSRB) and including cutting in all type soil (i.e. soil, rocky, semi rocky, concrete, asphalt and other layers) Earth Cutting Works: Supply materials and equipment to use in excavation of the cutting sections. Includes removal of the cutting material. Earth Filling Works: Supply materials and equipment for the filling sections. Sub-base & base layer works: Provide all requirements (including Batch plant) to lay a layer of crushed limestone base course with 40cm thick in three layers, 9 m width and well compacted to %98 of M.D.D according to the section "R7" and table ""Batch plant ksites. The Contractor shall leave the Worksite and close surrounding clean as directed by the Site Engineer.R7/1" in the "IGSRB" and the instructions of the site engineer. Culverts: Provide materials and construct complete concrete pipe & box culverts using fair face wood shuttering all exposed edge shall be chamfered. Double Box culvert 2x2 m Double Box culvert 1.5x1.5 m. Single Box culvert (1.5x1.5)m. 01 m double (Reinforced concrete) Ø1 m single (Reinforced concrete) Construction of New Pavement Prime coat to the requirements of section R&A of the IGSRB and the instructions of the Bituminous stabilizer course with the width of 7.85 meter according to the section R9 and the table R9/3 of SORB revised edition 2003 with the thickness of 10 cm. after compaction according to the site engineer and compaction of %97 density of Marshal laboratory. Notice: the rate of mixing bituminous for the stabilizer and using bulk density 40 to 50 grade and if there was any change in the mixture rate of the bituminous will be deducted according to the IGSRB of 1992 Tack coat to the requirements of section R&B of the IGSRB and the instructions of the site engineer. C.4.4 Bituminous binder course 7.5 meter wide, according to the section R9 and the table R9 Total Costs ($) 1,537,400.00 20,000.00 10,000.00 10,000.00 10,000.00 10,000.00 858,000.00 768,000.00 90,000.00 78,000.00 78,000.00 267,150.00 112,500.00 72,000.00 21,600.00 40,800.00 20,250.00 304,250.00 5,750.00 161,000.00 5,500.00 132,000.00 Total % Complete 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% 100% Work Completed Total Completed to Previous Application date ($) 1,537,400.00 20,000.00 10,000.00 10,000.00 10,000.00 10,000.00 858,000.00 768,000.00 90,000.00 78,000.00 78,000.00 267,150.00 112,500.00 72,000.00 21,600.00 40,800.00 20,250.00 304,250.00 5,750.00 161,000.00 5,500.00 132,000.00 1,537,400.00 20,000.00 10,000.00 10,000.00 10,000.00 10,000.00 858,000.00 768,000.00 90,000.00 78,000.00 78,000.00 267,150.00 112,500.00 72,000.00 21,600.00 40,800.00 20,250.00 304,250.00 5,750.00 161,000.00 5,500.00 132,000.00 This Period ($)
Expert Answer:
Answer rating: 100% (QA)
Excel Bank Reconciliation and Charts A Bank Statement Reconciliation Form Application Excel Complete Production Challenge 15C on page 325 of the textbook then create the bank reconciliation statement ... View the full answer
Related Book For
Microeconomics Theory and Applications with Calculus
ISBN: 978-0133019933
3rd edition
Authors: Jeffrey M. Perloff
Posted Date:
Students also viewed these accounting questions
-
Draw a cash flow diagram for the following cashflow: YEAR Receipts (S) Disbursements ($) 0 2 3 4 1,000 0 0 2,000 2,000 1,000 4,750 0 0 0
-
Draw a cash flow diagram for the following cashflow: YEAR Receipts (S) Disbursements ($) 2 3 4 0 5,000 5,000 0 0 5,000 7,500 5,000 0 0
-
Draw the cash flow diagram for the following statements: $70K Purchase price with 20% down ($14K) Monthly expenses (utilities, maintenance, insurance, etc..) = $200 Monthly P&I = $345 (starts in...
-
Draw a simple undirected graph G that has 12 vertices, 18 edges, and 3 connected components.
-
Explain how economies of scale can be a barrier to entry.
-
Transactions during 20X5, the first year of the newly organized Nancys Discount Foods Corporation, included the following: 2 Jan. Paid $ 12,000 lawyers fees and other related costs to register the...
-
Do the following activities to complete your marketing plan: 1. Draw a simple organizational chart for your organization. 2. Develop a Gantt chart (see Chapter 2) to schedule the key activities...
-
The Diamond Glitter Company is in the process of preparing its financial statements for 2012. Assume that no entries for depreciation have been recorded in 2012. The following information related to...
-
What do you mean by Hardware Software Interface? Give a concrete example. Define the two principle integrity rules for the relational model. Discuss why it is desirable to enforce these rules.
-
Determine the optical path difference for the two waves A and B, both having vacuum wavelengths of 500 nm, depicted in Fig. P.7.6; the glass (n = 1.52) tank is filled with water (n = 1.33). If the...
-
Calculate the 2022 Vertical Analysis "Inventory" in % using total assets as your base. Fill in the numerator and denominator using the financial statements provided (no symbols or commas) and the...
-
Write an assembly program to perform the following If sw1(PD0) =A If sw2(PD1)=A If sw3(PD2)=A If sw4(PD3) =A If sw5(PD4)=A If sw6(PD5)=A If sw7(PD6)=A If sw8(PD7)=A => The output of (PORT B) equal...
-
Which feature allows investors to withdraw their investment AND to receive the equivalent dollar amount of the net asset value of the units they own? Explain
-
What role does ethical stewardship play in the formulation and execution of leadership strategies, particularly in the context of corporate social responsibility and sustainable business practices?
-
Casa Loma Investment purchased a property for $10,000,000 and funded 75% of the acquisition using a long-term mortgage with an annual interest rate of 8%. Utilizing the Canadian mortgage formulas,...
-
a. Using rates from table calculate the 1-month forward contract premium or discount on Euro in %. (4 decimal places) b. Using rates from Table calculate the 2-month forward contract premium or...
-
Q2/congider bwo blags with a single feature X Problem with samples distributed according to the Rayleigh distribution in each class 25. P(x/wi) = Z X 1x70 2 2 e Compute the threshold value...
-
r = 0.18 Find the coefficients of determination and non-determination and explain the meaning of each.
-
What are the major differences between expected utility theory and prospect theory?
-
Remy views ice cream and fudge sauce as perfect complements. Is it possible that either of these goods or both of them are Giffen goods?
-
If an individual's labor supply curve slopes forward at low wages and bends backward at high wages, is leisure a Giffen good? If so, is leisure a Giffen good at high or low wage rates?
-
On November 15, 20X3, Chow Inc., a U.S. company, ordered merchandise FOB shipping point from a German company for 200,000. The merchandise was shipped and invoiced on December 10, 20X3. Chow paid the...
-
On April 8, 20X3, Trul Corporation purchased merchandise from an unaffiliated foreign company for 10,000 units of the foreign companys local currency. Trul paid the bill in full on March 1, 20X4,...
-
On September 1, 20X1, Cott Corporation received an order for equipment from a foreign customer for 300,000 LCUs when the U.S. dollar equivalent was $96,000. Cott shipped the equipment on October 15,...
Study smarter with the SolutionInn App