Question: make sure to use LPT ( Longest processing time) priority rule for requirement A Henri's Custom Gowns has six jobs waiting to be processed. Each

make sure to use LPT ( Longest processing time) priority rule for requirement A
Henri's Custom Gowns has six jobs waiting to be processed. Each gown is at the beading work center. The job information is shown here. Operations Job Time Remaining at Other at Other Work Work Centers Centers Days Until Due Job Time (in days) Job 8 34 8 3 B 10 40 4 5 C 6 25 6 2 D 8 22 12 3 E 9 31 10 5 F 5 15 ON 2 Step by Step Solution