Question: Make Sure while assigning the task that there are not more than the number of required Work Station (5), Thr cycle time= 1.2 and The

Make Sure while assigning the task that there are not more than the number of required Work Station (5), Thr cycle time= 1.2 and The minimum number of workstations is 5
Q1) Draw the precedence diagram.
Q2) Assign tasks to the required number of workstations and show the assignment of tasks in a diagram. ( Draw the diagram again with pointed relation of work station)
In order to complete the wing assembly for an experimental aircraft, a company has laid out the major steps and seven tasks involved. These tasks have been labeled A through G in the following table, which also shows their estimated completion times in minutes and immediate predecessors. Task Immediate Task time Predecessors (in minute) A 0.60 B A 0.55 0.80 D 0.70 E B,D 1.00 F B, E 0.80 G F 0.50Step by Step Solution
There are 3 Steps involved in it