Question: make the project start date 3 Jan 2022 Level the following multi-project operation. Work package Description Duration (weeks) Predecessors Resources A1 Analysis & design Proj
make the project start date 3 Jan 2022
Level the following multi-project operation.
| Work package | Description | Duration (weeks) | Predecessors | Resources |
| A1 | Analysis & design Proj 1 | 4 | - | SAD |
| B1 | Production Proj 1 | 7 | A1 | PROD |
| C1 | Testing Proj 1 | 3 | B1 | TEST |
| D1 | Install Proj 1 | 2 | C1 | INSTALL |
| A2 | Analysis & design Proj 2 | 4 | A1 | SAD |
| B2 | Production Proj 2 | 5 | A2 | PROD |
| C2 | Testing Proj 2 | 3 | B2 | TEST |
| D2 | Install Proj 2 | 1 | C2 | INSTALL |
| A3 | Analysis & design Proj 3 | 8 | A2 | SAD |
| B3 | Production Proj 3 | 12 | A3 | PROD |
| C3 | Testing Proj 3 | 5 | B3 | TEST |
| D3 | Install Proj 3 | 3 | C3 | INSTALL |
| A4 | Analysis & design Proj 4 | 8 | A3 | SAD |
| B4 | Production Proj 4 | 10 | A4 | PROD |
| C4 | Testing Proj 4 | 4 | B4 | TEST |
| D4 | Install Proj 4 | 2 | C4 | INSTALL |
1. show the schedual before the leveling
2. show the schedual of the project after leveling
3.If all work was to be done by the deadline of the end of week 40, what resources are causing delay?