Question: Management: 1a.What is the slack time for Activity B given the activity times and precedence requirements shown in the table? 1b.What is the late start
Management:
1a.What is the slack time for Activity B given the activity times and precedence requirements shown in the table?
1b.What is the late start time for Activity E given the activity times and precedence requirements shown in the table?
1c. What is the late finish time for Activity D given the activity times and precedence requirements shown in the table?
1d.What is the early start time for Activity G given the activity times and precedence requirements shown in the table?
| Activity | Time | Predecessor |
| A | 4 | -- |
| B | 7 | -- |
| C | 8 | A |
| D | 2 | A |