Question: Management has determined that your project must be completed by March 25. This date is an input to your planning process group and is considered
Management has determined that your project must be completed by March 25. This date is an input to your planning process group and is considered what?
aEnterprise environmental factor bConstraint cAssumption dOrganizational process assetStep by Step Solution