Question: Management put your project on hold for a few months, and now it's ready to start up again. Which Updet Project eptions ere appropriate to
Management put your project on hold for a few months, and now it's ready to start up again. Which Updet Project eptions ere appropriate to restart the project on the date you specify?
Select an answer:
the "Update work as complete through" option along with the "Set or complete only" option
the "Reschedule uncompleted work to start after" option along with the "Entire project" option
the "Update work as complete through" option along with the complete" option
the "Reschedule uncompleted work to start after" option along with the "Selected tasks" option