Question: managers would like to determine the total project completion time ( in days ) and those activities that lie along the critical path. The appropriate

managers would like to determine the total project completion time (in days) and those activities that lie along the critical path. The appropriate data are shown in the following table
Time (days)
Immediate
Predecessor(s)
Activity
Time (days)
Activity
a
b
a
m
b
Immediate
Predecessor(s)
A
4
6
7
H
5
5
8
E.F
B
2
2
3
1
5
10
G, H
C
6
6
6
A
J
2
4
8
D
4
9
12
A
K
8
12
1
E
3
9
19
B, C
L
2
4
7
J
F
1
4
8
D
M
1
2
4
K
G
1
5
8
D
N
6
9
11
L, M
a) The expected completion time of the project =5.83 days (round your response to two decimal places)
AKKKKKKKKKKKKKKKKKKKKKKKKKKKKK

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!