Question: Managing both throughput and theoretical flow time can control inventory. Theoretical in-process flow time can be reduced by a number of measures. Select the measure
Managing both throughput and theoretical flow time can control inventory. Theoretical in-process flow time can be reduced by a number of measures. Select the measure that is not applicable in reducing theoretical in-process flow time.
Question 14 options:
Reducing bottleneck activity times.
Moving work from critical to noncritical activities.
Managing buffer inventory.
Eliminating non-value-added activities.
Step by Step Solution
There are 3 Steps involved in it