Question: Many cases arise in which a contractor does not complete his contract on time due to excusable delay such as: an act of God, strikes,

Many cases arise in which a contractor does not complete his contract on time due to "excusable delay"
such as: an act of God, strikes, severe weather, or difficulty in obtaining materials. The most important
criterion in determining excusable delay is if the:
Select the single best answer:
A. contractor's financial loss would be large or slight.
B. delay is important to the owner.
C. contractor could have used other means.
D. causes of the delay could have been foreseen.