Question: Many different processes take place during an MRP calculation, which of the following statements is not correct Net requirements occur whghe gross requirements are larger

Many different processes take place during an MRP
Many different processes take place during an MRP calculation, which of the following statements is not correct Net requirements occur whghe gross requirements are larger than the combined opening inventory & scheduled receipts for that period The planned order release of the parent explodes to become the gross requirement of the components in the bill of materials structure Projected available indicates end of period" stock levels Net requirements will automatically generate scheduled receipts