Question: Many free and open source project management software programs are available online, such as Asana, BaseCamp, Bitrix24, GanttProject, MeisterTask, Trello, and Zoho. Choose one of

Many free and open source project management software programs are available online, such as Asana, BaseCamp, Bitrix24, GanttProject, MeisterTask, Trello, and Zoho. Choose one of these programs or use a spreadsheet or another project management program with which you are familiar. Create a Gantt chart using the values from the table below. How long will it take to complete a project consisting of these tasks? Identify the critical path for this project.

Task

Duration

Predecessor Task

A

5

B

3

C

4

A, B

D

8

D

E

5

C

F

3

D, E

I don't need the Chart I want an explanation, please explain

Many free and open source project management
Critical path = Task 1>2>4>5>6>7>8 Please find in image below the gantt chart. The total expected time of project = Sum of expected task time on critical path =109.76 Final answer Critical path = Task 1>2>4>5>6>7>8 Please find in image below the gantt chart. The total expected time of project = Sum of expected task time on critical path =109.76

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!