Marble Construction is remodeling an office building. There are 12 tasks which cannot be completed simultaneously as
Fantastic news! We've Found the answer you've been seeking!
Question:
Marble Construction is remodeling an office building. There are 12 tasks which cannot be completed simultaneously as some tasks can not be started until other tasks have been completed. The table shows each task, the time required to complete the task, and the tasks which must be completed before starting the task. Suppose that tasks can be worked concurrently as long as tasks dependencies are met. Formulate a linear or integer program that can be used to find the minimum duration of the remodel and the earliest time each task can be started.