Question: Marcus's manager asked how much time he needed to complete the project. Marcus estimated the project would take ten weeks, but to be safe, he

Marcus's manager asked how much time he needed to complete the project.
Marcus estimated the project would take ten weeks, but to be safe, he told his
manager it would take 12 weeks. This is an example of
planning horizon
contingencies
padding
 Marcus's manager asked how much time he needed to complete the