Question: Mariam Joseph on July 3 0 , 2 0 2 3 , sent a memo to her boss, the director of project management, stating that
Mariam Joseph on July sent a memo to her boss, the director of project management,
stating that the KTNGL project would require weeks for completion according to the figure below.
Mariam realized that the customer wanted the job completed in less time. After discussions with
the functional managers, Mariam developed the table shown below:
Activity Normal Normal Crash Crash Additional Crash
ID Time Cost Time Cost CostWeek
A
B
C
D
E
F
Total Direct Normal Costs $
Time unit Week