Question: Mariam Joseph on July 3 0 , 2 0 2 3 , sent a memo to her boss, the director of project management, stating that

Mariam Joseph on July 30,2023, sent a memo to her boss, the director of project management,
stating that the KTNGL project would require 13 weeks for completion according to the figure below.
Mariam realized that the customer wanted the job completed in less time. After discussions with
the functional managers, Mariam developed the table shown below:
Activity Normal Normal Crash Crash Additional (Crash)
ID Time Cost Time Cost Cost/Week
A 3600028,0002,000
B 512,000413,5001,500
C 516,000322,0003,000
D 48,000210,0001,000
E 26,00018,5002,500
F 314,000120,0003,000
Total Direct Normal Costs - $ 62,000
Time unit =1 Week

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!