Question: Mark determined the project he had been working on for two months was ready to close since all of the contracts were completed. Based on

Mark determined the project he had been working on for two months was ready to close since all of the contracts were completed.
Based on the current situation of Mark's project, select the next two steps below that he will perform in the closing process.
a.)
Meet with the project sponsor to gain project approval, then meet with the person responsible for taking ownership.
b.)
Refer to governance to determine the documentation left to complete, then meet with the project sponsor to gain project approval.
c.)
Obtain feedback to compile lessons learned, then meet with the person responsible for taking ownership.
d.)
Refer to governance to determine the documentation left to complete, then obtain feedback to compile lessons learned.

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!