Question: Mark works as a project manager for a midsized organization that uses Microsoft Project to carry out its work. He is managing a priority software
Mark works as a project manager for a midsized organization that uses Microsoft Project to carry out its work. He is managing a priority software development project that needs to be delivered on time. He's caught up with some personal issues due to which he is unable to report to the office for an entire week. Although any delay in the project is unacceptable. Which of the following options can he use to solve this issue? This type of question contains radio buttons and checkboxes for selection of options. Use Tab for navigation and Enter or space to select the option. option A Project baseline option B SharePoint option C Project Online option D Interim plan