Question: Marketing has requested that we create a production line for our new product, Widget Z. They believe that we will have a daily demand of

Marketing has requested that we create a production line for our new product, Widget Z. They believe that we will have a daily demand of 27,000 Widgets per day. With a 3-shift per day operation and a total of 1,290 minutes per day available for production, what is our TAKT time?


Step by Step Solution

3.32 Rating (143 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

To calculate the Takt time we need to divide the available production time by the ... View full answer