Question: Marle Construction enters into a contract with a customer to build a warehouse for 950,000 on March 30, 2018 with a performance bonus of 50,000
Marle Construction enters into a contract with a customer to build a warehouse for 950,000 on March 30, 2018 with a performance bonus of 50,000 if the building is completed by July 31, 2018. The bonus is mond by 10,000 each week that completion is delayed. Made commonly includes these completion bonum in its contracts and, based on prior experience, estimates the following completion outcomes: Completed by Probability July 31, 2018 65% August 7, 2018 25% 5% August 14, 2018 August 21. 2018 5% Determine the transaction price