Question: (a) (b) (c) (d) (e) (f) The table below depicts the WBS Dictionary for a software development project: Task Task A Duration (days) Dependency

(a) (b) (c) (d) (e) (f) The table below depicts the WBS

(a) (b) (c) (d) (e) (f) The table below depicts the WBS Dictionary for a software development project: Task Task A Duration (days) Dependency Resource Worker 1 Worker 1 Worker 2 Task D Worker 2 Task E Worker 3 Task F Worker 2 Task G Worker 1 Using any appropriate technique, calculate the duration of the project. Draw the resource usage graph for Worker 1, Worker 2, Worker 3. Task B Task C 2 3 2 1 2 1 2 A B C,D E F Comment on resource usage in this project and perform any required resource leveling. State any assumptions. State any THREE factors that you would consider when allocating work to different members of a team. The customer would like the project duration to be reduced. State THREE techniques by which individual task durations could be reduced. What are the possible pitfalls of each technique?

Step by Step Solution

3.48 Rating (164 Votes )

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock

a Using a critical path method we can calculate the duration of the project as follows Task A 2 days Task B 3 days Task C 2 days starts on day 2 Task ... View full answer

blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related Physics Questions!