Martin Weir, a project controller at MacDonald Soup Company, recently learned about the classic PERT method...
Fantastic news! We've Found the answer you've been seeking!
Question:
Transcribed Image Text:
Martin Weir, a project controller at MacDonald Soup Company, recently learned about the classic PERT method for planning under task time uncertainty. Mac's has previously used critical chain project management (CCPM) exclusively. Wanting to better understand how these two methods compare, Marty has asked you to do some comparative analysis. The table below provides Marty's planning estimates for a new project including tasks, precedence relations, durations for the PERT approximation, and task duration point estimates for use with CCPM. Mac's has standardized CCPM estimating, reducing duration estimates by 50% and calculating a project buffer as 38% of the makespan reduction. Marty would like the PERT project buffer to be a 90% confidence buffer. Because he has little experience with project management in general, he would like you to calculate the metrics shown below. Note: Round all answers to 2 decimal places. If asked to enter a path, enter the task id's separated with hyphens (e.g. start-A-C-end). PERT Expected Makespan: CCPM schedule confidence (per PERT): PERT Promise Date: PERT Project Buffer Size: CCPM Promise Date: CCPM Adj Makespan: Task Predecessors | Optimistic | Most Likely | Pessimistic start 0 0 0 A 51.6 24.9 36 25.9 38.8 B 39.3 C 28.8 33.3 38.1 39.4 13.7 D E F G H I J K L end start start A A.B B A C E.G H D.F D I.J.K L 31 16.1 22.9 12.9 32.1 35 23.1 0 47.4 18,7 35.7 16.3 37.2 15.6 36.8 45.8 26.4 0 Pessimistic CCPM Point Estimate 0 37.34 39.32 35.9 62.1 70.2 46.6 55.8 46.3 55.3 37.4 78 29.4 0 54.74 41.94 41.01 33.73 42.75 33.39 37.57 61.15 28.08 0 Martin Weir, a project controller at MacDonald Soup Company, recently learned about the classic PERT method for planning under task time uncertainty. Mac's has previously used critical chain project management (CCPM) exclusively. Wanting to better understand how these two methods compare, Marty has asked you to do some comparative analysis. The table below provides Marty's planning estimates for a new project including tasks, precedence relations, durations for the PERT approximation, and task duration point estimates for use with CCPM. Mac's has standardized CCPM estimating, reducing duration estimates by 50% and calculating a project buffer as 38% of the makespan reduction. Marty would like the PERT project buffer to be a 90% confidence buffer. Because he has little experience with project management in general, he would like you to calculate the metrics shown below. Note: Round all answers to 2 decimal places. If asked to enter a path, enter the task id's separated with hyphens (e.g. start-A-C-end). PERT Expected Makespan: CCPM schedule confidence (per PERT): PERT Promise Date: PERT Project Buffer Size: CCPM Promise Date: CCPM Adj Makespan: Task Predecessors | Optimistic | Most Likely | Pessimistic start 0 0 0 A 51.6 24.9 36 25.9 38.8 B 39.3 C 28.8 33.3 38.1 39.4 13.7 D E F G H I J K L end start start A A.B B A C E.G H D.F D I.J.K L 31 16.1 22.9 12.9 32.1 35 23.1 0 47.4 18,7 35.7 16.3 37.2 15.6 36.8 45.8 26.4 0 Pessimistic CCPM Point Estimate 0 37.34 39.32 35.9 62.1 70.2 46.6 55.8 46.3 55.3 37.4 78 29.4 0 54.74 41.94 41.01 33.73 42.75 33.39 37.57 61.15 28.08 0 Martin Weir, a project controller at MacDonald Soup Company, recently learned about the classic PERT method for planning under task time uncertainty. Mac's has previously used critical chain project management (CCPM) exclusively. Wanting to better understand how these two methods compare, Marty has asked you to do some comparative analysis. The table below provides Marty's planning estimates for a new project including tasks, precedence relations, durations for the PERT approximation, and task duration point estimates for use with CCPM. Mac's has standardized CCPM estimating, reducing duration estimates by 50% and calculating a project buffer as 38% of the makespan reduction. Marty would like the PERT project buffer to be a 90% confidence buffer. Because he has little experience with project management in general, he would like you to calculate the metrics shown below. Note: Round all answers to 2 decimal places. If asked to enter a path, enter the task id's separated with hyphens (e.g. start-A-C-end). PERT Expected Makespan: CCPM schedule confidence (per PERT): PERT Promise Date: PERT Project Buffer Size: CCPM Promise Date: CCPM Adj Makespan: Task Predecessors | Optimistic | Most Likely | Pessimistic start 0 0 0 A 51.6 24.9 36 25.9 38.8 B 39.3 C 28.8 33.3 38.1 39.4 13.7 D E F G H I J K L end start start A A.B B A C E.G H D.F D I.J.K L 31 16.1 22.9 12.9 32.1 35 23.1 0 47.4 18,7 35.7 16.3 37.2 15.6 36.8 45.8 26.4 0 Pessimistic CCPM Point Estimate 0 37.34 39.32 35.9 62.1 70.2 46.6 55.8 46.3 55.3 37.4 78 29.4 0 54.74 41.94 41.01 33.73 42.75 33.39 37.57 61.15 28.08 0 Martin Weir, a project controller at MacDonald Soup Company, recently learned about the classic PERT method for planning under task time uncertainty. Mac's has previously used critical chain project management (CCPM) exclusively. Wanting to better understand how these two methods compare, Marty has asked you to do some comparative analysis. The table below provides Marty's planning estimates for a new project including tasks, precedence relations, durations for the PERT approximation, and task duration point estimates for use with CCPM. Mac's has standardized CCPM estimating, reducing duration estimates by 50% and calculating a project buffer as 38% of the makespan reduction. Marty would like the PERT project buffer to be a 90% confidence buffer. Because he has little experience with project management in general, he would like you to calculate the metrics shown below. Note: Round all answers to 2 decimal places. If asked to enter a path, enter the task id's separated with hyphens (e.g. start-A-C-end). PERT Expected Makespan: CCPM schedule confidence (per PERT): PERT Promise Date: PERT Project Buffer Size: CCPM Promise Date: CCPM Adj Makespan: Task Predecessors | Optimistic | Most Likely | Pessimistic start 0 0 0 A 51.6 24.9 36 25.9 38.8 B 39.3 C 28.8 33.3 38.1 39.4 13.7 D E F G H I J K L end start start A A.B B A C E.G H D.F D I.J.K L 31 16.1 22.9 12.9 32.1 35 23.1 0 47.4 18,7 35.7 16.3 37.2 15.6 36.8 45.8 26.4 0 Pessimistic CCPM Point Estimate 0 37.34 39.32 35.9 62.1 70.2 46.6 55.8 46.3 55.3 37.4 78 29.4 0 54.74 41.94 41.01 33.73 42.75 33.39 37.57 61.15 28.08 0 Martin Weir, a project controller at MacDonald Soup Company, recently learned about the classic PERT method for planning under task time uncertainty. Mac's has previously used critical chain project management (CCPM) exclusively. Wanting to better understand how these two methods compare, Marty has asked you to do some comparative analysis. The table below provides Marty's planning estimates for a new project including tasks, precedence relations, durations for the PERT approximation, and task duration point estimates for use with CCPM. Mac's has standardized CCPM estimating, reducing duration estimates by 50% and calculating a project buffer as 38% of the makespan reduction. Marty would like the PERT project buffer to be a 90% confidence buffer. Because he has little experience with project management in general, he would like you to calculate the metrics shown below. Note: Round all answers to 2 decimal places. If asked to enter a path, enter the task id's separated with hyphens (e.g. start-A-C-end). PERT Expected Makespan: CCPM schedule confidence (per PERT): PERT Promise Date: PERT Project Buffer Size: CCPM Promise Date: CCPM Adj Makespan: Task Predecessors | Optimistic | Most Likely | Pessimistic start 0 0 0 A 51.6 24.9 36 25.9 38.8 B 39.3 C 28.8 33.3 38.1 39.4 13.7 D E F G H I J K L end start start A A.B B A C E.G H D.F D I.J.K L 31 16.1 22.9 12.9 32.1 35 23.1 0 47.4 18,7 35.7 16.3 37.2 15.6 36.8 45.8 26.4 0 Pessimistic CCPM Point Estimate 0 37.34 39.32 35.9 62.1 70.2 46.6 55.8 46.3 55.3 37.4 78 29.4 0 54.74 41.94 41.01 33.73 42.75 33.39 37.57 61.15 28.08 0 Martin Weir, a project controller at MacDonald Soup Company, recently learned about the classic PERT method for planning under task time uncertainty. Mac's has previously used critical chain project management (CCPM) exclusively. Wanting to better understand how these two methods compare, Marty has asked you to do some comparative analysis. The table below provides Marty's planning estimates for a new project including tasks, precedence relations, durations for the PERT approximation, and task duration point estimates for use with CCPM. Mac's has standardized CCPM estimating, reducing duration estimates by 50% and calculating a project buffer as 38% of the makespan reduction. Marty would like the PERT project buffer to be a 90% confidence buffer. Because he has little experience with project management in general, he would like you to calculate the metrics shown below. Note: Round all answers to 2 decimal places. If asked to enter a path, enter the task id's separated with hyphens (e.g. start-A-C-end). PERT Expected Makespan: CCPM schedule confidence (per PERT): PERT Promise Date: PERT Project Buffer Size: CCPM Promise Date: CCPM Adj Makespan: Task Predecessors | Optimistic | Most Likely | Pessimistic start 0 0 0 A 51.6 24.9 36 25.9 38.8 B 39.3 C 28.8 33.3 38.1 39.4 13.7 D E F G H I J K L end start start A A.B B A C E.G H D.F D I.J.K L 31 16.1 22.9 12.9 32.1 35 23.1 0 47.4 18,7 35.7 16.3 37.2 15.6 36.8 45.8 26.4 0 Pessimistic CCPM Point Estimate 0 37.34 39.32 35.9 62.1 70.2 46.6 55.8 46.3 55.3 37.4 78 29.4 0 54.74 41.94 41.01 33.73 42.75 33.39 37.57 61.15 28.08 0 Martin Weir, a project controller at MacDonald Soup Company, recently learned about the classic PERT method for planning under task time uncertainty. Mac's has previously used critical chain project management (CCPM) exclusively. Wanting to better understand how these two methods compare, Marty has asked you to do some comparative analysis. The table below provides Marty's planning estimates for a new project including tasks, precedence relations, durations for the PERT approximation, and task duration point estimates for use with CCPM. Mac's has standardized CCPM estimating, reducing duration estimates by 50% and calculating a project buffer as 38% of the makespan reduction. Marty would like the PERT project buffer to be a 90% confidence buffer. Because he has little experience with project management in general, he would like you to calculate the metrics shown below. Note: Round all answers to 2 decimal places. If asked to enter a path, enter the task id's separated with hyphens (e.g. start-A-C-end). PERT Expected Makespan: CCPM schedule confidence (per PERT): PERT Promise Date: PERT Project Buffer Size: CCPM Promise Date: CCPM Adj Makespan: Task Predecessors | Optimistic | Most Likely | Pessimistic start 0 0 0 A 51.6 24.9 36 25.9 38.8 B 39.3 C 28.8 33.3 38.1 39.4 13.7 D E F G H I J K L end start start A A.B B A C E.G H D.F D I.J.K L 31 16.1 22.9 12.9 32.1 35 23.1 0 47.4 18,7 35.7 16.3 37.2 15.6 36.8 45.8 26.4 0 Pessimistic CCPM Point Estimate 0 37.34 39.32 35.9 62.1 70.2 46.6 55.8 46.3 55.3 37.4 78 29.4 0 54.74 41.94 41.01 33.73 42.75 33.39 37.57 61.15 28.08 0 Martin Weir, a project controller at MacDonald Soup Company, recently learned about the classic PERT method for planning under task time uncertainty. Mac's has previously used critical chain project management (CCPM) exclusively. Wanting to better understand how these two methods compare, Marty has asked you to do some comparative analysis. The table below provides Marty's planning estimates for a new project including tasks, precedence relations, durations for the PERT approximation, and task duration point estimates for use with CCPM. Mac's has standardized CCPM estimating, reducing duration estimates by 50% and calculating a project buffer as 38% of the makespan reduction. Marty would like the PERT project buffer to be a 90% confidence buffer. Because he has little experience with project management in general, he would like you to calculate the metrics shown below. Note: Round all answers to 2 decimal places. If asked to enter a path, enter the task id's separated with hyphens (e.g. start-A-C-end). PERT Expected Makespan: CCPM schedule confidence (per PERT): PERT Promise Date: PERT Project Buffer Size: CCPM Promise Date: CCPM Adj Makespan: Task Predecessors | Optimistic | Most Likely | Pessimistic start 0 0 0 A 51.6 24.9 36 25.9 38.8 B 39.3 C 28.8 33.3 38.1 39.4 13.7 D E F G H I J K L end start start A A.B B A C E.G H D.F D I.J.K L 31 16.1 22.9 12.9 32.1 35 23.1 0 47.4 18,7 35.7 16.3 37.2 15.6 36.8 45.8 26.4 0 Pessimistic CCPM Point Estimate 0 37.34 39.32 35.9 62.1 70.2 46.6 55.8 46.3 55.3 37.4 78 29.4 0 54.74 41.94 41.01 33.73 42.75 33.39 37.57 61.15 28.08 0
Expert Answer:
Answer rating: 100% (QA)
CCPM Pain CCPM pain is the inability of a project manager to effectively manage a project that is in the Critical Chain Project Management CCPM methodology This pain is often caused by several factors ... View the full answer
Related Book For
Project Management The Managerial Process
ISBN: 9781260570434
8th Edition
Authors: Eric W Larson, Clifford F. Gray
Posted Date:
Students also viewed these business communication questions
-
In an effort to better understand how her investments are affected by market factors, Michelle Delatorre, the professional tennis player introduced in the Integrative Problem in Chapter, has posed...
-
To better understand how husbands and wives feel about their finances, Money Magazine conducted a national poll of 1010 married adults age 25 and older with household incomes of $50,000 or more...
-
Assist your organization's marketing department to better understand how consumers make economic decisions. Write and present an analysis including the following: Introduction and conclusion The...
-
Columbiana: A small, independent Caribbean island that wants to develop its tourist industry and attract more visitors. How can a Web presence help? What Internet business model would be appropriate?...
-
The condensed financial statements of Eau Fraiche Company for the years 2010 and 2011 are presented below. Compute the following ratios for 2010 and 2011. (a) Current ratio. (b) Inventory turnover....
-
Rework Problem 16.11 using a computer program with E = 3 Ã 107 psi, ( = 0.00073 lb-s2 /in4, A = 1 in2, L = 100 in., and I = 0.0833 in4. Figure P16-13 Refer to Problem 16.11, For the beams...
-
The following TI-84 Plus display presents the results of a test of the null hypothesis H0: 1 = 0. a. What is the alternate hypothesis? b. What is the value of the test statistic? c. How many degrees...
-
Sam Santiago operates a retail variety store. The books include a cash payments journal and an accounts payable ledger. All cash payments (except petty cash) are entered in the cash payments journal....
-
Pintime Industries Incorporated entered into a business combination agreement with Sydrolized Chemical Corporation (SCC) to ensure an uninterrupted supply of key raw materials and to realize certain...
-
Dylan Reyes is the accountant for Heads Up Hat Corporation. In preparing the payroll for the semimonthly pay period ending December 15, Dylan notices that some of the year-to-date executives salaries...
-
A 2kg block original at rest is being pushed by a force F at an angle of 0-30 below horizintal. The mass of the block is 2kg. The coefficients of static and kinetic friction between the block and the...
-
On ten days, a bank had 18, 15, 13, 12, 8, 3, 7, 14, 16, and 3 bad checks. Find the mean, median, variance, and standard deviation of the number of bad checks.
-
P(C|E c ) Find the indicated probabilities by referring to the given tree diagram and by using Bayess Rule. A P(A) = 0.2 P(E|A)=0.6 E P(ECA) = 0.4 -EC P(B) = 0.55 P(E|B)=0.7 -E B EC P(E|B) = 0.3 P(C)...
-
The following sample was taken from a normally distributed population with a known standard deviation = 4. Test the hypothesis that the mean = 20 using a level of significance of 0.05 and the...
-
Use the information given in Problem 23 to find: (a) P(A 1 |E) (b) P(A 2 |E) (c) P(A 3 |E) Data from Problem 23 Suppose that events A 1 , A 2 , and A 3 form a partition of the sample space S with P(A...
-
P(B|E) Find the indicated probabilities by referring to the given tree diagram and by using Bayess Rule. A P(A) = 0.2 P(E|A)=0.6 E P(ECA) = 0.4 -EC P(B) = 0.55 P(E|B)=0.7 -E B EC P(E|B) = 0.3 P(C) =...
-
In the reaction _S+302 2SO3, what coefficient should be placed in front of the S to balance the reaction?
-
In the series connection below, what are the respective power consumptions of R, R2, and R3? R R www 4 V=6V P1-3 W; P2=3W; and P3= 3 W OP10.5 W; P2-1 W; and P3= 1.5 W P1=1.5 W; P2=1 W; and P3= 0.5 W...
-
1 . Can you identify personal examples of white elephants? 2 . What else do you think Olympic organizers could do to make the event more sustainable?
-
What could the NBA have done differently to increase the likelihood of success?
-
How important is a fun culture for innovation?
-
Figure 1.101 shows an offset slider-crank mechanism with a crank length \(r\), connecting rod length \(l\), and offset \(\delta\). If the crank has a mass and mass moment of inertia of \(m_{r}\) and...
-
Find a single equivalent damping constant for the following cases: a. When three dampers are parallel. b. When three dampers are in series. c. When three dampers are connected to a rigid bar (Fig....
-
Design a piston-cylinder-type viscous damper to achieve a damping constant of \(175 \mathrm{~N}-\mathrm{s} / \mathrm{m}\) using a fluid of viscosity \(35 \times 10^{-3} \mathrm{~N}-\mathrm{s} /...
Study smarter with the SolutionInn App