Question: Masters Machine Shop is considering a four-year project to improve its production efficiency. Buying a new machine press for $1,142,400 is estimated to result in

| Masters Machine Shop is considering a four-year project to improve its production efficiency. Buying a new machine press for $1,142,400 is estimated to result in $380,800 in annual pretax cost savings. The press falls in the MACRS five-year class (MACRS Table), and it will have a salvage value at the end of the project of $166,600. The press also requires an initial investment in spare parts inventory of $47,600, along with an additional $7,140 in inventory for each succeeding year of the project. |
| If the shop's tax rate is 21 percent and its discount rate is 12 percent, what is the NPV for this project? |
Multiple Choice
-
$14,824.49
-
$18,360.77
-
$-108,777.05
-
$15,565.72
-
$14,083.27
Year 1 Property Class Three-Year Five-Year 33.33% 20.00% 44.45 32.00 14.81 19.20 7.41 11.52 11.52 5.76 Seven-Year 14.29% 24.49 17.49 12.49 8.93 8.92 8.93 4.46
Step by Step Solution
There are 3 Steps involved in it