Question: Match each description with the appropriate contracting method. Question 6 options: 1 2 3 CM takes no entrepreneurial risk for costs, timeliness, or quality of
Match each description with the appropriate contracting method.
Question options:
CM takes no entrepreneurial risk for
costs, timeliness, or quality of
construction, and all subcontractors
contract directly with the owner.
Owner retains direct contractual control
over design and construction
DesignBidBuild
Design Build
Agency Construction Management
More effective way to fast track a
project
Acts as the owner's agent in supervising
and coordinating all aspects of the
construction project from the beginning
of design to the end of construction.
Competitive process usually develops
very competitive bids.
Step by Step Solution
There are 3 Steps involved in it
1 Expert Approved Answer
Step: 1 Unlock
Question Has Been Solved by an Expert!
Get step-by-step solutions from verified subject matter experts
Step: 2 Unlock
Step: 3 Unlock