Question: Match each example to it's risk strategy.3.v Removing a part of the project that is determined high riskAvoid Hiring a specialist / expertTransfer Hire two
Match each example to it's risk strategy.3.v Removing a part of the project that is determined high riskAvoid Hiring a specialist / expertTransfer Hire two companies to test the security of the new software3.megate Weather might delay the project. A cost estimate is created to cover this if is happens.Accept Partner with another company of the projectShare If we finish the project ahead of time, the company wal be able to taike on an additional desired project. We add more resources to try to finish ahead of time.Enhance7, The project manager knows that if the key stakeholders are kept updated on the2.Exploit project, they have committed to additional resources if needed. The project manager holds regular meetings with the stakeholders.