Match Point, Inc. has the following overhead standards: Variable overhead: 5 hours at $7 per hour Fixed
Fantastic news! We've Found the answer you've been seeking!
Question:
Variable overhead: 5 hours at $7 per hour
Fixed overhead: 5 hours at $9 per hour
- The standards were based on a planned activity of 35,000 machine hours when 7,000 units were scheduled for production.
- Actual data follow.
Fixed overhead incurred: $375,000
Machine hours worked: 34,800
Actual units produced: 7,100
What is Match Point’s fixed-overhead volume variance ?