Question: Match Point, Inc. has the following overhead standards: Variable overhead: 5 hours at $7 per hour Fixed overhead: 5 hours at $9 per hour The
Variable overhead: 5 hours at $7 per hour
Fixed overhead: 5 hours at $9 per hour
- The standards were based on a planned activity of 35,000 machine hours when 7,000 units were scheduled for production.
- Actual data follow.
Fixed overhead incurred: $375,000
Machine hours worked: 34,800
Actual units produced: 7,100
What is Match Point’s fixed-overhead volume variance ?
Step by Step Solution
3.51 Rating (144 Votes )
There are 3 Steps involved in it
Standard machine hours allowed can be calculated using the planned activity level and the standard t... View full answer
Get step-by-step solutions from verified subject matter experts