Question: Match the following terms with their definitions The difference between the earned value and the actual costs for the work completed to date Total Budgeted

Match the following terms with their definitions
Match the following terms with their definitions
Match the following terms with their definitions The difference between the earned value and the actual costs for the work completed to date Total Budgeted cost of the project baseline V The percentage of the original budget that has been earned by actual work completed. 1. Earned Value 2. Planned Value 3. Actual Cost The estimated cost at the completion of the project calculated as the actual costs plus the estimated cost remaining on the project. 4. Cost Variance 5. Schedule Variance V The sum of the costs incurred in accomplishing 6. Budgeted Cost at Completion MAM 2. Planned Value V 3. Actual Cost The estimated cost at the completion of the project calculated as the actual costs plus the estimated cost remaining on the project. 4. Cost Variance 5. Schedule Variance V The sum of the costs incurred in accomplishing work 6. Budgeted Cost at Completion 7. Estimated Cost at Completion V The difference between the earned value and baseline to date. 8. Cost Variance at Completion An approved cost estimate of the resources scheduled in a time-phased culumulative baseline. Expected actual over- or underrun costat completion

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!