Question: Match the project characteristic to the framework/approach. Question 1 options: Facilitates a reduction in uncertainty Scrum is an example of this project approach May use
Match the project characteristic to the framework/approach. Question 1 options: Facilitates a reduction in uncertainty Scrum is an example of this project approach May use an iterative and incremental development approach The project has uncertainty or risk specifically related to the requirements The primary purpose is to provide value to the organization 1. Predictive 2. Hybrid 3. Adaptive 4. Hybrid or Adaptive 5. Predictive, Hybrid or Adaptive