Question: Match the situations in which the EAC formulas may be used to the appropriate formulas for those situations. When variances are not expected to occur

Match the situations in which the EAC formulas may be used to the appropriate formulas for those situations.

When variances are not expected to occur for the remainder of the project

Answer 1

Choose...EAC = BAC + AC - EV

EAC = BAC / cumulative CPI EAC = AC + bottom-up ETC. EAC = AC + [(BAC - EV) / (cumulative CPI cumulative SPI)]

When you estimate future costs for work packages and aggregate these costs

Answer 2

Choose...EAC = BAC + AC - EV.

EAC = BAC / cumulative CPI. EAC = AC + bottom-up ETC. EAC = AC + [(BAC - EV) / (cumulative CPI cumulative SPI)]

When you take the project's cost performance into account and don't expect the CPI to change

Choose...EAC = BAC + AC - EV.

EAC = BAC / cumulative CPI. EAC = AC + bottom-up ETC. EAC = AC + [(BAC - EV) / (cumulative CPI cumulative SPI)]

When you take both the project's cost and schedule performance into account

Choose...EAC = BAC + AC - EV. EAC = BAC / cumulative CPI. EAC = AC + bottom-up ETC. EAC = AC + [(BAC - EV) / (cumulative CPI cumulative SPI)]

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!