Question: Match the situations in which the EAC formulas may be used to the appropriate formulas for those situations. When variances are not expected to occur
Match the situations in which the EAC formulas may be used to the appropriate formulas for those situations.
When variances are not expected to occur for the remainder of the project | Answer 1 Choose...EAC = BAC + AC - EV EAC = BAC / cumulative CPI EAC = AC + bottom-up ETC. EAC = AC + [(BAC - EV) / (cumulative CPI cumulative SPI)] |
When you estimate future costs for work packages and aggregate these costs | Answer 2 Choose...EAC = BAC + AC - EV. EAC = BAC / cumulative CPI. EAC = AC + bottom-up ETC. EAC = AC + [(BAC - EV) / (cumulative CPI cumulative SPI)] |
When you take the project's cost performance into account and don't expect the CPI to change | Choose...EAC = BAC + AC - EV. EAC = BAC / cumulative CPI. EAC = AC + bottom-up ETC. EAC = AC + [(BAC - EV) / (cumulative CPI cumulative SPI)] |
When you take both the project's cost and schedule performance into account | Choose...EAC = BAC + AC - EV. EAC = BAC / cumulative CPI. EAC = AC + bottom-up ETC. EAC = AC + [(BAC - EV) / (cumulative CPI cumulative SPI)] |
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
