Question: Match the term to the best definition / related statement Total Slack Free Slack Lags Positive Slack Negative Slack Milestones Finish to Start Start to

Match the term to the best definition/related statement
Total Slack
Free Slack
Lags
Positive Slack
Negative Slack
Milestones
Finish to Start
Start to Start
Finish to Finish
Start to Finish
[ Choose]
the amount of time that a task in a project network can be delayed without causing a delay to subsequent tasks. the finish of one task is dependent on another task starting.
the start of one task is dependent on another task finishing.
the amount of time that a task in a project network can be delayed without causing a delay to the project completion date.
Doesn't use up resources or time, and doesn't add any direct costs to our project. Used to mark important events.
Doesn't use up resources and doesn't add any direct costs to our project. Adds time to forward pass calculations.
Our project is behind schedule.
the finish time of one task is dependent on another task finishing.
Our project is ahead of schedule.
the start of one task is dependent on another task starting.
 Match the term to the best definition/related statement Total Slack Free

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!