Question: Match the term with the correct definition: Planned Value Earned Value Schedule Variance Budget at Completion Cost Variance Schedule Performance Index Actual Costs Cost Performance
Planned Value Earned Value Schedule Variance Budget at Completion Cost Variance Schedule Performance Index Actual Costs Cost Performance Index 1. the amount of money that the project is expected to spend on project activities at a given point in time. 2. how much money was actually spent on an activity at a given time 3. how much work was actually completed on the project at the given point in time 4. sum of the planned value for all the activities (budget baseline) 5. earned value minus actual costs 6. earned value minus planned value 7. provides an indicator of the overall cost performance to date 8. provides an indicator of the overall schedule performance to date
Step by Step Solution
There are 3 Steps involved in it
Get step-by-step solutions from verified subject matter experts
