Question: Matrix Functional QUESTION 2 A project team member is talking to another team member and complaining that many people are asking him to do things.

Matrix
Functional
QUESTION 2
A project team member is talking to another team member and complaining that many people are asking him to do things. If he works in
1. The PMO
2. The project manager
3. The team
4. The functional manager