Question: Matthew is managing a specific task. The task's budget is $ 4 , 0 0 0 and is scheduled for four months. After the first

Matthew is managing a specific task. The task's budget is $4,000 and is scheduled for four months. After the first month, Matthew has spent $750, and only 20% of the project has been completed. What is the cost variance? Is project cost on track?
Group of answer choices
CV is $800. This is positive and the project is under budget.
CV is $50. This is positive and the project is under budget.
CV is $50. This is positive and the project is over budget.
CV is $800. This is positive and the project is over budget.