Question: Maximizing Project Acceleration Within Budget: Using the attached project data (with monetary values in MGA), how can I maximize project acceleration while adhering to a

Maximizing Project Acceleration Within Budget: Using the attached project data (with monetary values in MGA), how can I maximize project acceleration while adhering to a budget constraint of 640,000,000 MGA? I'm looking for specific recommendations for the Board of Directors of the Bank of Africa, including the accelerated project timeline, additional costs, and an execution profile. Please focus on the Excel process, formulas, and steps to arrive at these conclusions.

Activity Description Predecessors Duration (Weeks) Accelerated (Weeks) Resources (MGA) Accelerated Cost (MGA)
A Selection of Microcredit Office Location None 4 2 200000000 400000000
B Development of Organizational and Budgetary Plan None 6 3 150000000 300000000
C Human Resources Staffing Requirements B 4 2 70000000 140000000
D Physical Resources Office Design A,C 5 3 12000000 24000000
E Physical Resources Interior Construction D 9 4 25000000 50000000
F Human Resources Select Staff to Transfer C 3 2 12000000 24000000
G Human Resources Hire New Employees F 5 3 15000000 30000000
H Systems Assign Passwords/Codes F 3 2 3000000 6000000
I Tesoreria Apartar los recursos de acuerdo al presupuesto B 6 3 12000000 24000000
J Human Resources Train New Staff E,G 4 2 8000000 16000000
K Physical Resources Development of Advertising I 2 1 25000000 50000000
L Physical Resources Distribute Advertising to Media K 3 2 12000000 24000000
M Assignment of Responsibilities J 2 1 2000000 4000000
N Opening of New Office M, H, I 1 1 16000000 32000000

Step by Step Solution

There are 3 Steps involved in it

1 Expert Approved Answer
Step: 1 Unlock blur-text-image
Question Has Been Solved by an Expert!

Get step-by-step solutions from verified subject matter experts

Step: 2 Unlock
Step: 3 Unlock

Students Have Also Explored These Related General Management Questions!